[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260909":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1260909,844,2,"多选题","横道进度计划的缺点是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","复杂、难编制",false,{"key":16,"text":17,"correct":18},"B","不能全面反映工作之间的逻辑关系",true,{"key":20,"text":21,"correct":18},"C","不能客观地突出重点",{"key":23,"text":24,"correct":18},"D","不能从图中看出计划的潜力",{"key":26,"text":27,"correct":14},"E","不便于统计资源","BCD","工序（工作）之间的逻辑关系可以设法表达，但不易表达清楚。（2）适用于手工编制计划；（3）没有通过严谨的进度计划时间参数计算，不能确定计划的关键工作、关键路线与时差（4）计划调整只能用手工方式进行，其工作量较大；（5）难以适应大的进度计划系统。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]