[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260908":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1260908,844,1,"单选题","出现了进度偏差，是因为业主拖欠工程款，这个原因属于以下（ ）因素。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工期及相关计划的失误",false,{"key":16,"text":17,"correct":14},"B","工程条件的变化",{"key":19,"text":20,"correct":21},"C","管理过程中的失误",true,{"key":23,"text":24,"correct":14},"D","其他原因","业主拖欠工程款，出现了进度偏差属于管理过程中的失误。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]