[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260905":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1260905,844,1,"单选题","检查和调整施工进度计划不包括（ ）的检查与调整。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工工期",false,{"key":16,"text":17,"correct":18},"B","施工方案",true,{"key":20,"text":21,"correct":14},"C","施工顺序",{"key":23,"text":24,"correct":14},"D","资源均衡性","检查和调整施工进度计划不包括施工方案的检查与调整。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]