[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260903":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1260903,844,1,"单选题","因为计划值不足，相关的实际工作量增加，出现了进度偏差，属于（ ）因素。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工期及相关计划的失误",true,{"key":16,"text":17,"correct":18},"B","工程条件的变化",false,{"key":20,"text":21,"correct":18},"C","管理过程中的失误",{"key":23,"text":24,"correct":18},"D","其他原因","计划值不足，相关的实际工作量增加，出现了进度偏差属于工期及相关计划的失误。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]