[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260902":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1260902,844,2,"多选题","指导性施工进度计划适用于（ ）的工程。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","任务具体明确",true,{"key":16,"text":17,"correct":14},"B","施工条件基本落实",{"key":19,"text":20,"correct":21},"C","结构较复杂",false,{"key":23,"text":24,"correct":14},"D","各项资源供应正常",{"key":26,"text":27,"correct":14},"E","施工工期不太长","ABDE","指导性施工进度计划适用于任务具体明确、施工条件基本落实、各项资源供应正常、施工工期不太长的工程。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]