[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260899":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1260899,844,2,"多选题","检查和调整施工进度计划不包括哪些方面（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工工期的检查与调整",false,{"key":16,"text":17,"correct":18},"B","施工方案的检查与调整",true,{"key":20,"text":21,"correct":14},"C","施工顺序的检查与调整",{"key":23,"text":24,"correct":14},"D","资源均衡性的检查与调整",{"key":26,"text":27,"correct":18},"E","施工组织的检查与调整","BE","检查和调整施工进度计划包括：施工工期的检查与调整、施工顺序的检查与调整、资源均衡性的检查与调整。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]