[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260896":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1260896,844,2,"多选题","施工进度计划根据施工项目划分的粗细程度划分不包括哪些（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","年进度计划",true,{"key":16,"text":17,"correct":18},"B","控制性施工进度计划",false,{"key":20,"text":21,"correct":14},"C","季进度计划",{"key":23,"text":24,"correct":18},"D","指导性施工进度计划",{"key":26,"text":27,"correct":14},"E","月进度计划","ACE","施工进度计划根据施工项目划分的粗细程度可分为指导性施工进度计划和控制性施工进度计划两类。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]