[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260895":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1260895,844,2,"多选题","编制施工进度计划的工具有很多，主要有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","控制性计划",false,{"key":16,"text":17,"correct":18},"B","横道图计划",true,{"key":20,"text":21,"correct":18},"C","网络计划",{"key":23,"text":24,"correct":14},"D","实施性计划",{"key":26,"text":27,"correct":14},"E","专项计划","BC","编制施工进度计划的工具包括：横道图计划、网络计划等。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]