[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260893":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1260893,844,2,"多选题","当进度出现偏差时，应考虑有关因素，分析产生的原因，其主观因素有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工期及相关计划的失误",true,{"key":16,"text":17,"correct":18},"B","发生公共事件",false,{"key":20,"text":21,"correct":18},"C","工程条件的变化",{"key":23,"text":24,"correct":14},"D","管理过程中的失误",{"key":26,"text":27,"correct":18},"E","遇到暴雪天气","AD","当进度出现偏差时，应考虑有关因素，分析产生的原因，其主观因素有工期及相关计划的失误、管理过程中的失误。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]