[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260892":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1260892,844,2,"多选题","在项目实施过程中，应定期地跟踪检查施工实际进度情况，确定实际进度与计划进度之间的关系，其主要工作包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","分析计划进度",false,{"key":16,"text":17,"correct":18},"B","跟踪检查工程实际进度",true,{"key":20,"text":21,"correct":18},"C","整理统计跟踪检查数据",{"key":23,"text":24,"correct":18},"D","对比实际进度与计划进度",{"key":26,"text":27,"correct":18},"E","工程项目进度检查结果的处理","BCDE","在项目实施过程中，应定期地跟踪检查施工实际进度情况，确定实际进度与计划进度之间的关系，其主要工作包括跟踪检查工程实际进度、整理统计跟踪检查数据、对比实际进度与计划进度、工程项目进度检查结果的处理。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]