[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260888":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1260888,844,3,"判断题","若出现进度偏差的工作为非关键工作，而该工作的进度偏差小于其总时差，则对后续工作和总工期均不产生影响。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"若出现进度偏差的工作为非关键工作，而该工作的进度偏差小于其总时差，则总工期无影响。",{"id":6,"name":21,"category":22,"favorite":23},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]