[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260884":3},{"question":4,"library":19},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":9},1260884,844,3,"判断题","若出现进度偏差的工作为关键工作，则无论偏差大小，都会对后续工作和总工期产生影响。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,{"id":6,"name":20,"category":21,"favorite":22},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]