[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260876":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1260876,844,1,"单选题","下列选项中，会造成费用增加，且加剧资源供应的困难的，是（ ）进度计划的调整方法。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","增加资源投入",true,{"key":16,"text":17,"correct":18},"B","改变工作逻辑关系",false,{"key":20,"text":21,"correct":18},"C","资源供应的调整",{"key":23,"text":24,"correct":18},"D","提高劳动生产率","会造成费用增加，且加剧资源供应的困难的，是增加资源投入进度计划的调整方法。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]