[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260875":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1260875,844,1,"单选题","必须经过上层管理者，如投资者、业主的批准的进度计划调整方法是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","采用新技术，减少资源投入",false,{"key":16,"text":17,"correct":14},"B","改变工作的逻辑关系",{"key":19,"text":20,"correct":21},"C","增减工作的范围",true,{"key":23,"text":24,"correct":14},"D","提高劳动生产率","必须经过上层管理者，如投资者、业主的批准的进度计划调整方法是增减工作的范围。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]