[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260873":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1260873,844,1,"单选题","工程项目的控制性实施进度计划与工程项目中的（ ）一一对应。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工总进度计划",false,{"key":16,"text":17,"correct":18},"B","单位工程施工进度计划",true,{"key":20,"text":21,"correct":14},"C","分部分项工程施工进度计划",{"key":23,"text":24,"correct":14},"D","专项工程施工进度计划","工程项目的控制性实施进度计划与工程项目中的单位工程施工进度计划一一对应。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]