[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260871":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1260871,844,1,"单选题","下列属于实施性进度计划的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","控制性进度计划",false,{"key":16,"text":17,"correct":14},"B","施工总进度计划",{"key":19,"text":20,"correct":21},"C","月度施工季度计划",true,{"key":23,"text":24,"correct":14},"D","横道进度计划","实施性施工计划：由施工单位在项目施工时根据工程实际情况编制，主要用于施工期间各项资源配置落实，并对工程实体组织实施的计划依据。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]