[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260843":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1260843,844,1,"单选题","关于分部（分项）工程作业计划，以下表述正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","是以群体工程为施工组织对象进行编制的",false,{"key":16,"text":17,"correct":14},"B","是以单位工程为对象编制的",{"key":19,"text":20,"correct":21},"C","以某些主要的或新结构、技术复杂的或缺乏施工经验的分部（分项）工程为对象编制的",true,{"key":23,"text":24,"correct":14},"D","设计单位和总分包单位参加共同编制","分部（分项）工程作业计划：是以某些主要的或新结构、技术复杂的或缺乏施工经验的分部（分项）工程为对象编制的。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]