[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260817":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1260817,844,2,"多选题","设备安装与装饰工程中的施工顺序正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","先进行设备管线的安装，再进行建筑装饰装修工程的施工",true,{"key":16,"text":17,"correct":14},"B","在预埋阶段，先通风、后水暖管道、再电器线路",{"key":19,"text":20,"correct":21},"C","总的规律是封闭+预埋+装饰",false,{"key":23,"text":24,"correct":14},"D","封闭阶段，先墙面、后顶面、再地面",{"key":26,"text":27,"correct":14},"E","装饰阶段，先油漆、后裱糊、再面板","ABDE","总的规律是预埋+封闭+装饰。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]