[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260815":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1260815,844,1,"单选题","室内排水管道及配件安装施工工艺流程：（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","安装准备→预制加工→支架安装→干管安装→立管安装→支管安装→封口堵洞→闭水实验",true,{"key":16,"text":17,"correct":18},"B","预制加工→安装准备→支架安装→干管安装→立管安装→支管安装→封口堵洞→闭水实验",false,{"key":20,"text":21,"correct":18},"C","预制加工→安装准备→干管安装→支架安装→立管安装→支管安装→封口堵洞→闭水实验",{"key":23,"text":24,"correct":18},"D","预制加工→安装准备→支架安装→立管安装→干管安装→支管安装→封口堵洞→闭水实验","室内排水管道及配件安装施工工艺流程：安装准备→预制加工→支架安装→干管安装→立管安装→支管安装→封口堵洞→闭水实验。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]