[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260789":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1260789,844,2,"多选题","室内装饰装修工程，施工施工顺序应根据具体条件来确定，基本原则有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","先湿作业、后于作业",true,{"key":16,"text":17,"correct":18},"B","先下后上",false,{"key":20,"text":21,"correct":14},"C","先墙顶、后地面",{"key":23,"text":24,"correct":18},"D","先外后内",{"key":26,"text":27,"correct":14},"E","先管线、后饰面","ACE","室内装饰装修工程，施工施工顺序应根据具体条件来确定，基本原则是：“先湿作业、后于作业”，“先墙顶、后地面”，“先管线、后饰面”。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]