[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260745":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1260745,844,1,"单选题","确定施工流向时，工程各部位的繁简程度，哪些部位应适当靠后施工（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","技术复杂",false,{"key":16,"text":17,"correct":14},"B","施工进度较慢",{"key":19,"text":20,"correct":14},"C","工期较长",{"key":22,"text":23,"correct":24},"D","体型复杂",true,"工程各部位的繁简程度。一般对技术复杂、施工进度较慢、工期较长的工段或部位先施工。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]