[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260727":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1260727,844,1,"单选题","确定室内装饰主要项目施工顺序，说法错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","先湿作业后装饰",false,{"key":16,"text":17,"correct":14},"B","先楼上后楼下",{"key":19,"text":20,"correct":21},"C","先近后远",true,{"key":23,"text":24,"correct":14},"D","先顶、墙面后地面","室内装饰主要项目施工顺序包括：先湿作业后装饰、先楼上后楼下、先顶、墙面后地面。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]