[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260371":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1260371,843,3,"判断题","整体面层验收中的一般项目：应70％以上的检查点（处），符合规范规定的质量要求；其他检查点（处）不得有明显影响使用，且最大偏差值不超过允许偏差值的50％为合格。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"整体面层验收中的一般项目：应80％以上的检查点（处），符合规范规定的质量要求；其他检查点（处）不得有明显影响使用，且最大偏差值不超过允许偏差值的50％为合格。",{"id":6,"name":21,"category":22,"favorite":23},"(装饰施工)基础知识","建筑工程",0]