[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260149":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1260149,843,2,"多选题","某建筑工程，分部分项工程费为3574262.64元，施工技术措施费为1201876.52元，试计算其单位工程招标控制价。假设其施工组织措施费费率为3.8%，规费费率为6.35％，税金费率为3.41％。根据背景资料，回答下列问题。 本工程的含税工程造价由（ ）费用相加而得。（多项选择题）",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","施工组织措施费",true,{"key":16,"text":17,"correct":14},"B","规费",{"key":19,"text":20,"correct":14},"C","税金",{"key":22,"text":23,"correct":14},"D","其他项目费",{"key":25,"text":26,"correct":27},"E","其他措施费",false,"ABCD","含税工程造价包括：施工组织措施费、规费、税金、其他项目费",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)基础知识","建筑工程",0]