[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260141":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1260141,843,2,"多选题","编制竣工结算时，属于可以调整的工程量差有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建设单位提出的设计变更",true,{"key":16,"text":17,"correct":18},"B","由于某种建筑材料一时供应不上，需要改用其他材料代替",false,{"key":20,"text":21,"correct":14},"C","施工中遇到需要处理的问题而引起的设计变更",{"key":23,"text":24,"correct":18},"D","施工中返工造成的工程量差",{"key":26,"text":27,"correct":14},"E","施工图预算分项工程量不准确","ACE","可以调整的工程量差有：1.建设单位提出的设计变更2.施工中遇到需要处理的问题而引起的设计变更3.施工图预算分项工程量不准确",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)基础知识","建筑工程",0]