[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260139":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1260139,843,2,"多选题","在可调价格合同中，价款调整的范围包括（ ）方式。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","国家法律、行政法规和国家政策变化",true,{"key":16,"text":17,"correct":14},"B","工程造价管理部门公布的价格调整",{"key":19,"text":20,"correct":21},"C","工程量的增加",false,{"key":23,"text":24,"correct":21},"D","不可抗力事件",{"key":26,"text":27,"correct":14},"E","发包人更改经审定批准的施工组织设计（修正错误除外）造成费用增加","ABE","价款调整的范围包括：国家法律、行政法规和国家政策变化；工程造价管理部门公布的价格调整；发包人更改经审定批准的施工组织设计（修正错误除外）造成费用增加。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)基础知识","建筑工程",0]