[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260119":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1260119,843,2,"多选题","招标单位在编制标底时需考虑的因素包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","材料价格因素",true,{"key":16,"text":17,"correct":14},"B","B工程质量因素",{"key":19,"text":20,"correct":14},"C","工期因素",{"key":22,"text":23,"correct":24},"D","本招标工程资金来源因素",false,{"key":26,"text":27,"correct":14},"E","本招标工程的自然地理条件和招标工程范围等因素","ABCE","招标单位在编制标底时需考虑的因素包括：1.材料价格因素2.工程质量因素3.工期因素4.本招标工程的自然地理条件和招标工程范围等因素",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)基础知识","建筑工程",0]