[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260005":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1260005,843,2,"多选题","施工阶段的主要工作包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","由项目经理部编制开工报告",true,{"key":16,"text":17,"correct":14},"B","项目经理部抓紧做好各项施工准备",{"key":19,"text":20,"correct":14},"C","企业管理层委派项目经理",{"key":22,"text":23,"correct":24},"D","项目经理组织招聘劳务班组",false,{"key":26,"text":27,"correct":24},"E","项目经理组织购买大宗材料","ABC","施工阶段的主要工作包括：1.做好动态控制工作，保证质量、进度、成本、安全目标的全面实现2.管理施工现场，实现文明施工3.严格履行合同，协调好与建设单位、监理单位、设计单位等相关单位的关系4.处理好合同变更及索赔5.做好记录、检查、分析和改进工作。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)基础知识","建筑工程",0]