[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1259966":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1259966,843,2,"多选题","下列关于水泥砂浆地面施工要点中正确的是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","地面抹灰前，应先在四周墙上弹出一道水平基准线，作为确定水泥砂浆面层标高的依据",true,{"key":16,"text":17,"correct":14},"B","水平基准线做法是以设计地面标高为依据，在四周墙上弹出500mm作为水平基准线",{"key":19,"text":20,"correct":14},"C","水泥砂浆面层施工完毕后，要及时进行浇水养护，必要时可蓄水养护",{"key":22,"text":23,"correct":24},"D","水泥砂浆面层养护时间不少于3天",false,{"key":26,"text":27,"correct":24},"E","水泥砂浆面层强度等级不应小于35MPa","ABC","弹线找规矩：地面抹灰前，应先在四周墙上弹出一道水平基准线，作为确定水泥砂浆面层标高的依据。做法是以设计地面标高为依据，在四周墙上弹出500mm或1000mm作为水平基准线。养护。水泥砂浆面层施工完毕后，要及时进行浇水养护，必要时可蓄水养护，养护时间不少于7天，强度等级不应小于15MPA.",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)基础知识","建筑工程",0]