[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1259673":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1259673,843,1,"单选题","预制混凝土构件的工程量计算，遵循统筹图计算程序安排的原则（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","共性和在一起",false,{"key":16,"text":17,"correct":14},"B","个性分别处理",{"key":19,"text":20,"correct":14},"C","先主后次",{"key":22,"text":23,"correct":24},"D","独立项目单独处理",true,"预制混凝土构件、钢窗或木门窗、金属或木构件、钢筋用量、台阶、楼梯、地沟等独立项目的工程量计算，与墙的长度、僵住面积没有关系，不能合在一起，也不能用“线”、“面”基数计算时，需要单独处理。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)基础知识","建筑工程",0]