[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1259668":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1259668,843,1,"单选题","在下列情况下，承包人工期不予顺延的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人未按时提供施工条件",false,{"key":16,"text":17,"correct":18},"B","设计变更造成工期延长，但此项有时差可利用",true,{"key":20,"text":21,"correct":14},"C","一周内非承包人原因停水、停电、停气造成停工累计超过8h",{"key":23,"text":24,"correct":14},"D","不可抗力事件","设计变更造成工期延长，但此项有时差可利用，有时差可利用，不予补偿工期",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)基础知识","建筑工程",0]