[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1259660":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1259660,843,1,"单选题","（ ）是建设过程的最后一环，是投资转人生产或使用成果的标志。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","竣工验收",true,{"key":16,"text":17,"correct":18},"B","生产准备",false,{"key":20,"text":21,"correct":18},"C","建设准备",{"key":23,"text":24,"correct":18},"D","后评价阶段","竣工验收是建设过程的最后一环，是投资转人生产或使用成果的标志。，竣工验收是建立在分阶段验收的基础之上，前面已经完成验收的工程项目一般在房屋竣工验收时就不再重新验收。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)基础知识","建筑工程",0]