[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1259639":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1259639,843,1,"单选题","在预算定额人工工日消耗量计算时，已知完成单位合格产品的基本用工为22工日，超运距用工为4工日，辅助用工为2工日，人工幅度差系数为12%，则预算定额中的人工工日消耗量为（ ）工日。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3.36",false,{"key":16,"text":17,"correct":14},"B","25.36",{"key":19,"text":20,"correct":14},"C","28",{"key":22,"text":23,"correct":24},"D","31.36",true,"用工包括基本用工和其他用工，其他用工包括：辅助用工、超运距用工、人工幅度差，人工幅度差=（基本用工+辅助用工+超运距用工）×人工幅度差系数T=22+2+4+（4+2+22）*12%=31.36（工日）",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)基础知识","建筑工程",0]