[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1259635":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1259635,843,1,"单选题","工程量清单计价规范规定，对清单工程量以外的可能发生的工程量变更应在（ ）费用中考虑。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分部分项工程费",false,{"key":16,"text":17,"correct":14},"B","零星工程项目费",{"key":19,"text":20,"correct":21},"C","预留金",true,{"key":23,"text":24,"correct":14},"D","措施项目费","工程量清单计价规范规定，对清单工程量以外的可能发生的工程量变更应在预留金费用中考虑。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)基础知识","建筑工程",0]