[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1259624":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":24},1259624,843,1,"单选题","工程量清单漏项或由于设计变更引起新的工程量清单项目，其相应综合单价（ ）作为结算的依据。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由监理师提出，经发包人确认后",false,{"key":16,"text":17,"correct":18},"B","由承包方提出，经发包人确认后",true,{"key":20,"text":21,"correct":14},"C","由承包方提出，经监理师确认后",{"key":23,"text":21,"correct":14},"D","工程量清单漏项或由于设计变更引起新的工程量清单项目，其相应综合单价由承包方提出，经发包人确认后作为结算的依据。",{"id":6,"name":26,"category":27,"favorite":28},"(装饰施工)基础知识","建筑工程",0]