[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1259622":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1259622,843,1,"单选题","工程量清单编制原则归纳为“四统一，下列错误的提法是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目编码统一",false,{"key":16,"text":17,"correct":14},"B","项目名称统一",{"key":19,"text":20,"correct":21},"C","计价依据统一",true,{"key":23,"text":24,"correct":14},"D","工程量清单计算规则统一","四统一是指：项目编码统一、工程量清单计算规则统一、统一计量单位，项目名称统一。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)基础知识","建筑工程",0]