[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1259164":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1259164,842,3,"判断题","锤击法打桩时，当桩的规格、埋深、长度不同时，宜采用的打桩顺序为“先大后小、先深后浅、先短后长”。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"锤击法打桩时，当桩的规格、埋深、长度不同时，宜“先大后小、先深后浅、先长后短”施打。",{"id":6,"name":21,"category":22,"favorite":23},"(土建施工)专业管理实务 岗位知识","建筑工程",0]