[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1259148":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1259148,842,3,"判断题","记录施工情况包括：记录单位工程名称、开工时间、完成时间、施工工艺、完成情况、未完成情况、未完成原因及其他情况等。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"记录施工情况包括：记录分部分项工程名称、开工时间、完成时间、施工工艺、完成情况、未完成情况、未完成原因及其他情况等。",{"id":6,"name":21,"category":22,"favorite":23},"(土建施工)专业管理实务 岗位知识","建筑工程",0]