[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1259140":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1259140,842,3,"判断题","当设计无要求时，后张法预应力混凝土结构底模拆除应在预应力钢筋张拉前。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"拆除框架结构模板的顺序：首先是柱模板，然后是楼板底板，梁侧模板，最后梁底模板；拆除跨度较大的梁下支柱时，应先从跨中开始，分别拆向两端。",{"id":6,"name":21,"category":22,"favorite":23},"(土建施工)专业管理实务 岗位知识","建筑工程",0]