[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1259131":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1259131,842,3,"判断题","采用工程量清单方式招标，招标工程量清单必须作为招标文件的组成部分，其准确性和完整性由招标代理人负责。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"招标工程量清单必须作为招标文件的组成部分，其准确性和完整性由招标人负责。招标工程量清单应以单位（项）工程为单位编制，由分部分项工程量清单，措施项目清单，其他项目清单，规费清单，税金项目清单组成。",{"id":6,"name":21,"category":22,"favorite":23},"(土建施工)专业管理实务 岗位知识","建筑工程",0]