[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1259122":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":19},1259122,842,3,"判断题","在工程实施过程中，当项目特征发生了变化，发承包双方应当按照实际施工的项目特征，重新确定相应工程量清单项目的综合单价，调整合同价款。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,"在工程实施过程中，当项目特征发生了变化，发承包双方应当按照实际施工的项目特征，重新确定相应工程量清单项目的综合单价，调整合同价款。",{"id":6,"name":21,"category":22,"favorite":23},"(土建施工)专业管理实务 岗位知识","建筑工程",0]