[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1259117":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1259117,842,3,"判断题","若工作的进度偏差大于自由时差，说明该工作对后续工作有影响，原计划必须全部调整。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"若工作的进度偏差大于该工作的自由时差，说明此偏差对后续工作产生影响，应该如何调整，应根据后续工作允许影响的程度而定I若工作的进度偏差小于或等于该工作的自由时差，则说明此偏差对后续工作无影响，原进度计划可以不做调整。",{"id":6,"name":21,"category":22,"favorite":23},"(土建施工)专业管理实务 岗位知识","建筑工程",0]