[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1259082":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1259082,842,3,"判断题","室内装修工程的施工顺序有整体顺序自上而下和整体顺序自下而上两种，其中整体顺序自下而上的施工顺序是指主体结构施工到两层以上时，室内抹灰从底层开始逐层向上进行，一般与主体结构平行搭接施工。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"整体顺序自下而上的施工顺序是指主体结构施工到三层以上时，室内抹灰从底层开始逐层向上进行，一般与主体结构平行搭接施工。",{"id":6,"name":21,"category":22,"favorite":23},"(土建施工)专业管理实务 岗位知识","建筑工程",0]