[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1259026":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1259026,842,3,"判断题","施工项目成本计划只需要满足合同规定的工期就可以了。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"施工项目成本计划应包括从开工到竣工所必需的施工成本，它是该施工项目降低成本的指导文件，是设立目标成本的依据。施工项目成本计划的编制依据包括投标报价书、施工预算、施工组织设计或方案、有关财务成本核算制度和财务历史资料、拟采取的降低施工成本措施等。",{"id":6,"name":21,"category":22,"favorite":23},"(土建施工)专业管理实务 岗位知识","建筑工程",0]