[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258988":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":19},1258988,842,3,"判断题","总时差是指在不影响总工期的前提下，本工作可以利用的机动时间。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,"工作时差分为总时差和自由时差。总时差是指在不影响总工期的前提下，本工作可以利用的机动时间。",{"id":6,"name":21,"category":22,"favorite":23},"(土建施工)专业管理实务 岗位知识","建筑工程",0]