[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258939":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1258939,842,2,"多选题","项目实施过程中，发生下列（ ）情况之一时，专项施工方案应及时进行修改或补充。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","工程设计有重大修改",true,{"key":16,"text":17,"correct":14},"B","有关法律、法规、规范和标准实施、修订和废止",{"key":19,"text":20,"correct":14},"C","主要施工方法有重大调整",{"key":22,"text":23,"correct":24},"D","更换项目经理",false,{"key":26,"text":27,"correct":14},"E","施工环境有重大改变","ABCE","项目实施过程中，工程设计有重大修改，有关法律、法规、规范和标准实施、修订和废止，主要施工方法有重大调整，施工环境有重大改变专项施工方案应及时进行修改或补充。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)专业管理实务 岗位知识","建筑工程",0]