[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258938":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1258938,842,2,"多选题","单位工程的项目施工过程中，施工组织设计应及时进行修改或补充的情况有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程设计有重大修改",true,{"key":16,"text":17,"correct":18},"B","工期延误",false,{"key":20,"text":21,"correct":14},"C","主要施工资源配置有重大调整，如施工环境有重大改变",{"key":23,"text":24,"correct":14},"D","主要施工方法有重大调整",{"key":26,"text":27,"correct":14},"E","有关法律、法规、规范和标准实施、修订和废止","ACDE","单位工程的项目施工过程中，发生以下情况之一时，施工组织设计应及时进行修改或补充：①工程设计有重大修改；②有关法律、法规、规范和标准实施、修订和废止；③主要施工方法有重大调整；④主要施工资源配置有重大调整，如施工环境有重大改变。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)专业管理实务 岗位知识","建筑工程",0]