[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258912":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1258912,842,2,"多选题","安装作业前，安装单位应根据施工升降机（ ）等相关资料，确定所安装的施工升降机和辅助起重设备的基础、地基承载力、预埋件、基础排水措施等符合施工升降机安装、拆卸工程专项施工方案的要求。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","使用说明书",false,{"key":16,"text":17,"correct":14},"B","出厂合格证",{"key":19,"text":20,"correct":21},"C","隐蔽工程验收单",true,{"key":23,"text":24,"correct":21},"D","混凝土强度报告",{"key":26,"text":27,"correct":21},"E","基础验收表","CDE","安装作业前，安装单位应根据施工升降机隐蔽工程验收单，基础验收表混凝土强度报告，等相关资料，确定所安装的施工升降机和辅助起重设备的基础、地基承载力、预埋件、基础排水措施等符合施工升降机安装、拆卸工程专项施工方案的要求。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)专业管理实务 岗位知识","建筑工程",0]