[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258902":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1258902,842,2,"多选题","因发生不可抗力事件导致人员的伤亡、财产损失及其费用增加，发承包双方承担并调整合同价款的原则有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","发包人、承包人人员伤亡由对方单位负责，并承担相应费用",false,{"key":16,"text":17,"correct":18},"B","承包人的施工机械设备损坏及停工损失，由承包人承担",true,{"key":20,"text":21,"correct":14},"C","停工期间，承包人应发包人要求留在施工现场的必要的管理人员及保卫人员的费用由承包人承担",{"key":23,"text":24,"correct":18},"D","工程所需清理、修复费用，由发包人承担",{"key":26,"text":27,"correct":18},"E","发包人要求承包人赶工的，承包人应采取赶工措施，赶工费用由发包人承担","BDE","因发生不可抗力事件导致人员的伤亡、财产损失及其费用增加，发承包双方承担并调整合同价款的原则有承包人的施工机械设备损坏及停工损失，由承包人承担，工程所需清理、修复费用，由发包人承担和发包人要求承包人赶工的，承包人应采取赶工措施，赶工费用由发包人承担。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)专业管理实务 岗位知识","建筑工程",0]