[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258901":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1258901,842,2,"多选题","计日工是为了解决现场发生的零星工作的计价而设立的，在计日工表中应由招标人填写的项目有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","项目名称",true,{"key":16,"text":17,"correct":14},"B","暂定数量",{"key":19,"text":20,"correct":14},"C","计量单位",{"key":22,"text":23,"correct":24},"D","实际数量",false,{"key":26,"text":27,"correct":24},"E","综合单价","ABC","计日工是为了解决现场发生的零星工作的计价而设立的，在计日工表中应由招标人填写的项目有项目名称，暂定数量和计量单位。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)专业管理实务 岗位知识","建筑工程",0]